Name of work | RKI-IV/8-Rehabilitation and Upgradation of the road Veeyapuram-Edathua-Puthukkary-MambuzhakkaryKidangara-Kunnamgary-Valady-Mulakkamthuruthy Road (Length 21.457 Km) in Alappuzha District under Rebuild Kerala Initiative(RKl) |
Status of work | Agreement Executed |
Type of contract | Item Rate Contract |
Agreement No with date | 343/KSTP/PMT/PWD/2021 dated 03-03-2021 |
Name of Contractor | M/s Sreedhanya Construction Company |
Contract Amount | Rs 108,88,79,773.21/- |
Supervising method | Construction Supervision Consultant (CSC) |
Supervising agency | |
Date of commencement | |
Time of completion as per agreement | 18 months from the date of commencement. |
Date of completion | |
Extended date of completion/Actual date of completion | |
Maintenance period | 5 years |
Physical Progress | |
Financial Progress | |