Name of work | Rehabilitation and Upgradation of Thattarambalam – Michel Junction – Kochalummood – Mangankuzhy – Pandalam Road( Length 18.657 km) in Alappuzha district |
Status of work | Agreement executed |
Type of contract | Item Rate Contract |
Agreement No with date | 353/KSTP/PMT/PWD/2021 dated 29/04/2021 |
Name of Contractor | M/s Begorra- PRL (JV) |
Contract Amount | Rs.119,13,36,470/- |
Supervising method | Construction Supervision Consultant (CSC) |
Supervising agency | |
Date of commencement | |
Time of completion as per agreement | 18 months from the date of commencement. |
Date of completion | |
Extended date of completion/Actual date of completion | |
Maintenance period | 5 years |
Physical Progress | |
Financial Progress | |