Name of work | Rehabilitation and Upgrading the road Perambilavu to Nilambur section of SH39 from Km 30.700 to Km 62.480 (Length of 30.88 Km Excluding Km 35.975 to 36.425 and Km 58.500 to 58.950) in Malapuram District |
Status of work | Ongoing |
Type of contract | EPC Contract |
Agreement No with date | 330/KSTP/PMT/PWD/2020 dated 07-10-2020 |
Name of Contractor | M/s KMC Constructions Ltd. |
Contract Amount | Rs. 144,00,00,000/- |
Supervising method | Authority Engineer |
Supervising agency | M/s. Egis India Consulting Engineers Pvt Ltd –Orion Infra Consulting Pvt Ltd-(JV) |
Date of commencement | 20-01-2021 |
Time of completion as per agreement | 18 months |
Date of completion | 22-07-2022 |
Extended date of completion/Actual date of completion | |
DLP period | 5 Years |
Physical Progress | |
Financial Progress | |