Name of work | Upgrading Punalur to Ponkunnam road (SH 8) – Package 8C: Km 60+000 (Placherry) to Km 82+173 (Ponkunnam) |
Status of work | Ongoing |
Type of contract | EPC Mode |
Agreement No with date | 308/KSTP/PMT/PWD/2019 dated 24.09.2019 |
Name of Contractor | M/s Sreedhanya-Nath JV |
Contract Amount | Rs. 248.63 Crores |
Supervising method | Authority Engineer |
Supervising agency | M/s Consulting Engineers Group Limited |
Date of commencement/Appointment date | 23.12.2019 |
Time of completion as per agreement | 02 Years |
Date of completion | 22.12.2021 |
Extended date of completion/Actual date of completion | |
DLP period | 05 Years |
Physical Progress | 78.00% |
Financial Progress | 75.01% |