Name of work | Construction of Thiruvalla Bypass along Chengannur-Ettumanur Road from chainage Km 7+390 to Km 9+400 – Balance works |
Status of work | Ongoing |
Type of contract | Item rate contract |
Agreement No with date | 290/KSTP/PMT/PWD/2018 dated 29-12-2018 |
Name of Contractor | M/s GHV India Pvt. Ltd, Mumbai |
Contract Amount | Rs. 37,03,87,635/-. |
Supervising method | Construction Supervision Consultant |
Supervising agency | M/s Egis International in JV with M/s Egis India Pvt. Ltd. |
Date of commencement | 07-01-2019 |
Time of completion as per agreement | 09 months |
Date of completion | 06-10-2019 |
Extended date of completion/Actual date of completion | 14.02.2021 |
DLP period | 365 days |
Physical Progress | 99 % |
Financial Progress | 78 % |