Name of work | Upgrrdation of the Road from Kalarode (km 30+000) to Valavupara (Km 55+200) of SH-30 Balance works |
Status of work | On going |
Type of contract | Item rate |
Agreement No with date | No.275/KSTP/PMT/PWD/2016 dated 29-04-2016 |
Name of Contractor | M/s GHV-EKK (JV) |
Contract Amount | Rs. 209,68,48,832/- |
Supervising method | Construction Supervision Consultant |
Supervising agency | M/s Egis International in JV with M/s Egis India Consulting Engineers Pvt.Ltd. |
Date of commencement | 26-09-2016 |
Time of completion as per agreement | 24 Months |
Date of completion | 25-09-2018 |
Extended date of completion/Actual date of completion | EOT-4
For completion of Iritty Bridge & its approaches- up to 31-07-2020
For completion of Koottupuzha Bridge & its approaches- up to 31-04-2021
|
DLP period | 365 days |
Physical Progress | 95.15% |
Financial Progress | 90.74% |