Works

Name of work Upgrrdation of the Road from Kalarode (km 30+000) to Valavupara (Km 55+200) of SH-30 Balance works
Status of workOn going
Type of contractItem rate
Agreement No with dateNo.275/KSTP/PMT/PWD/2016 dated 29-04-2016
Name of ContractorM/s GHV-EKK (JV)
Contract AmountRs. 209,68,48,832/-
Supervising methodConstruction Supervision Consultant
Supervising agencyM/s Egis International in JV with M/s Egis India Consulting Engineers Pvt.Ltd.
Date of commencement26-09-2016
Time of completion as per agreement24 Months
Date of completion25-09-2018
Extended date of completion/Actual date of completionEOT-4
For completion of Iritty Bridge & its approaches- up to 31-07-2020
For completion of Koottupuzha Bridge & its approaches- up to 31-04-2021
DLP period365 days
Physical Progress95.15%
Financial Progress90.74%

Status of Road Works

Status of Iritty Bridge @ Km 42+198

Status of Kuttupuzha Bridge Works@ Km 53+865

Status of Other Bridge Works