Name of work | Up gradation of Chemmannar- Gap Road (Km 0+000 to to 29+935) under Re-build Kerala Initiative |
Status of work | Agreement Executed |
Type of contract | EPC Mode |
Agreement No with date | 327/KSTP/PMT/PWD/2020 dated 03-08-2020 |
Name of Contractor | DRAIPL-Greenworth (JV) |
Contract Amount | Rs.146,67,25,000/- |
Supervising method | Authority Engineer |
Supervising agency | M/s Consulting Engineers Group Limited |
Date of commencement | 18-08-2020 |
Time of completion as per agreement | 12 Months |
Date of completion | 17-08-2021 |
Extended date of completion/Actual date of completion | |
DLP period | 05 Years |
Physical progress | 7.34% |
Financial progress | 0.00% |