Works

Name of work BC Overlay to Adoor to Chengannur Road (Part of SH-1) Km 93+400 (Adoor) to Km 117+200 (Chengannur)
Status of workOngoing
Type of contractEPC Mode
Agreement No with date320/KSTP/PMT/PWD/2020 dated 24.01.2020
Name of ContractorM/s EKK Infrastructure Limited
Contract Amount98,10,00,000/-
Supervising methodAuthority Engineer
Supervising agencyM/s Consulting Engineers Group Limited
Date of commencement/Appointment date30-03-2020
Time of completion as per agreement12 Months
Date of completion29-03-2021
Extended date of completion/Actual date of completion
DLP period05 Years
Physical progress70.05 %
Financial progress55.04%

Status of Road Works

Status of Structure Works

Progress Photos