Name of work | KSTP-II/UG-6-Upgradation of Road from Ponkunnam (84+00) to Thodupuzha (130+363) and Thodupuzha Bypass of SH-8 |
Status of work | Completed |
Type of contract | Item rate |
Agreement No with date | No 239/KSTP/PMT/PWD/2014 dated 05-05-2014 |
Name of Contractor | M/s GHV-EKK (JV) |
Contract Amount | Rs 227,13,73,548/- |
Supervising method | Construction Supervision Consultant |
Supervising agency | M/s MSV International Inc. |
Date of commencement | 10-06-2014 |
Time of completion as per agreement | 30 Months |
Date of completion | 09-12-2016 |
Extended date of completion/Actual date of completion | 28-03-2017 |
DLP period | 365 days |