Name of work | KSTP-II/UG-2-Upgradation of the road from Pilathara (0+00) to Pappinissery (20+90) of SH-67 |
Status of work | Completed |
Type of contract | Item rate |
Agreement No with date | No 207/KSTP/PMT/PWD/2013 dated 01-04-2013 |
Name of Contractor | M/s RDS Project Ltd |
Contract Amount | Rs 118,29,77,833/- |
Supervising method | Construction Supervision Consultant |
Supervising agency | M/s Egis International in JV with M/s Egis India Consulting Engineers Pvt. Ltd. |
Date of commencement | 24-04-2013 |
Time of completion as per agreement | 24 Months |
Date of completion | 23-04-2015 |
Extended date of completion/Actual date of completion | Whole work except Ramapuram Bridge and Thavam ROB-31-03-2018
Ramapuram Bridge and Thavam ROB-31-08-2018 |
DLP period | 365 days |