Works

Name of work KSTP-II/UG-1-Up-gradation of Kasargod-Kanhangad Road (km: 0+000 to km:27+780)
Status of workCompleted
Type of contractItem rate
Agreement No with dateNo 206/KSTP/PMT/PWD/2013 dated 01-04-2013
Name of ContractorM/s. RDS Project
Contract AmountRs. 133,05,79,485/-
Supervising methodConstruction Supervision Consultant
Supervising agencyM/s Egis International in JV with M/s Egis India Consulting Engineers Pvt. Ltd.
Date of commencement24-04-2013
Time of completion as per agreement24 Months
Date of completion23-04-2015
Extended date of completion/Actual date of completion
DLP period365 days

Status of Road Works

Status of Bridge Works

Photo Gallery